Co-packing lead time vs full production: week by week

Tea co-packing lead time is 2-4 weeks; full production runs 8-14 weeks. See the week-by-week schedule and what slows each path down.

Luan Fazliu27 July 20269 min read

Tea production lead time is the number buyers get wrong most often. The 2-4 weeks quoted for co-packing and the 8-14 weeks for full production both have conditions attached - and the gap between best-case and worst-case can stretch a launch by months. This post runs the week-by-week schedule for both paths, names the specific steps that cause delays, and tells you what to do to stay at the short end of the range.

Calendar and journal on a green desk with a cup of tea, representing production planning and scheduling

The two paths: co-packing vs full production

Co-packing lead time starts after you have shipped your tea to our facility. You supply the tea, we supply the machine, the bag, the envelope, the string, and the tag. The production process is shorter because we skip recipe development, sourcing, and blending.

Full production lead time starts from an initial recipe brief. We source the herbs (many from family-cultivated fields in Kosovo and the wider Balkans region - the same supply chain Luan Fazliu has run since 1990), develop the blend, quality-check the raw material, then run production.

Neither clock starts from your first email. It starts from: confirmed order + deposit paid + approved artwork (co-packing) or confirmed recipe brief + deposit paid (full production).

Co-packing: the 2-4 week schedule

WeekStepWhat happensCommon delay
Week 0Order confirmationDeposit received, artwork files submitted, bag size confirmed (60x40mm or 64x44mm)Artwork not print-ready; buyer sends RGB instead of CMYK
Week 1Plate productionTag artwork sent to plate supplier; plate etched and returnedPlate supplier backlog; 2-3 day extension
Week 1-2Tea receipt + QCYour tea arrives at facility; we weigh, sample, and QC against specTea in transit delay; customs hold on import
Week 2Production runPT-2.33 scheduled and run; 5,000 bags take ~30-35 minutes at 150-160 bags/minMachine scheduling conflict on busy weeks
Week 2-3Pack + quality checkBags counted into cartons, labelled, palletised; final count verifiedRarely a delay source
Week 3-4DispatchEx-works Kosovo; freight to your warehouse per agreed IncotermsCarrier availability; cross-border customs

The best-case co-packing run is 2 weeks: artwork is print-ready on day one, your tea arrives in good time, machine scheduling has an open slot, and your freight carrier moves fast. The 4-week scenario is still within range but assumes one or two of those steps take an extra 3-5 days each.

If you are working to a retailer launch date or a trade show shipping deadline, target 5 weeks from order confirmation as your planning buffer. That gives you one week of slack without needing to escalate anything.

Full production: the 8-14 week schedule

Week rangeStepWhat happensCommon delay
Week 1Recipe brief + confirmationBuyer submits flavor profile, quality parameters, and target market; we confirm feasibility and raw material availabilityUnclear brief requires revision round
Week 1-2Raw material sourcingHerbs and botanicals sourced from our supply network; samples pulled for review if new ingredientsSeasonal availability; import from outside Kosovo
Week 2-4Blending + recipe developmentBatches blended to hit target flavor profile; internal tasting and approvalFlavor revision requested by buyer (adds 1-2 weeks per round)
Week 4-5Buyer sample approvalSample batch sent to buyer; buyer approves or requests adjustmentSlow buyer sign-off; revision adds another week
Week 5-6Artwork + plate productionPackaging design finalised; tag plate etchedArtwork revisions; designer availability on buyer side
Week 6-9Full production runRaw material scaled up; full run on PT-2.33; QC throughoutLarge volume runs over multiple shifts
Week 9-11Pack + inspectionFinal count, carton packing, pallet build, documentation for exportCertificate of analysis, food safety documents
Week 11-14Dispatch + transitEx-works Kosovo; freight to destination warehouseCustoms, carrier scheduling

The 8-week full production scenario requires: a clear recipe brief from day one, no flavor revision rounds, buyer sample sign-off within 48 hours, print-ready artwork on submission, and smooth freight. That happens with experienced buyers who have done this before.

The 14-week scenario is common for first-time full production buyers: one recipe revision round, one artwork revision, and standard freight transit. It is not a failure - it is a realistic planning number for a first run.

What slows a co-packing run

Artwork delays

The single most common co-packing delay is artwork. A co-packer needs print-ready files: CMYK color profile, vector artwork (AI or EPS preferred, high-res PDF accepted), bleed and safe zone set to the tag dimensions, and font outlines converted.

If you send a logo as a JPG or a Canva export, the plate supplier has to redraw it. That adds 3-5 days minimum and a redraw fee.

Fix: Before you place the order, have a designer produce a print-ready file. If you do not have one, tell us - we handle the design side on full production projects and can extend that service to co-packing artwork on request.

Tea in transit

Your tea needs to arrive at our facility before we can schedule the run. If your tea is coming from a supplier in India, Sri Lanka, or South America, factor in shipping time plus our import customs clearance. We are located in Kosovo - not an EU member state - so imports from outside the region go through customs processing. Budget 5-7 working days for customs on most standard commercial tea shipments.

If your tea is already in an EU warehouse, you can ship it to us via road freight. Transit time from Germany to Kosovo is typically 3-4 days. From North Macedonia or Albania, it is 1-2 days.

Woman in a business setting reviewing planning documents on an office wall, representing supply chain and production scheduling

Machine scheduling

The PT-2.33 runs at 150-160 bags/min. A 5,000-bag run takes under 40 minutes of machine time. But "machine time" is not the same as "scheduled slot." The machine may be mid-way through a 100,000-bag run for another customer. Small co-packing orders are scheduled into available windows between larger runs.

If your order arrives on a Monday and the machine is fully booked through Thursday, your slot starts Friday. That is 4 days of scheduling overhead with zero production inefficiency on our end.

The fix: tell us your deadline upfront. If you need goods ready by a specific date, we schedule backward from that date and tell you the latest acceptable order confirmation date.

What slows a full production run

Recipe revision rounds

Each revision round adds 7-14 days. Buyers who send a detailed brief - target flavor profile with reference teas, target market (what consumers in that country expect from this tea type), hard ingredient exclusions, and target price point - get a sample that lands close on the first try. Buyers who send "something like chamomile but different" generate multiple rounds.

The most productive brief format: share 2-3 commercially available teas that are close to what you want. We can reverse-engineer a flavor direction from examples much faster than from abstract descriptions.

Buyer sample sign-off

We ship a sample batch. Buyers need to taste, approve, and respond. The fastest buyers turn this around in 24-48 hours. The slowest take 3-4 weeks because the sample gets routed through a purchasing committee or a flavor panel.

If you know your approval process is slow, factor that into the 8-14 week estimate explicitly. The production clock is paused at "waiting for buyer approval."

Ingredient sourcing for unusual botanicals

Common Balkan herbs - chamomile, peppermint, sage, linden flower, mountain tea (sideritis), rosehip - are in our regular supply chain. Lead time for these is 1-2 weeks from brief to confirmed stock.

Unusual botanicals - specific single-origin cultivars, specialty adaptogens, or ingredients outside our standard supplier network - add 2-4 weeks for sourcing, quality testing, and import (if not locally available).

Our herb supply network benefits from 36 years of relationships across Kosovo, North Macedonia, and Albania built through the family herb business. That makes local Balkan botanicals faster to source than equivalent ingredients at most European co-packers. For ingredients outside that network, we are honest about sourcing timelines.

Female worker in uniform writing in a notebook inside a warehouse, representing quality control and production documentation

Side-by-side summary

FactorCo-packingFull production
You supplyTea (ready to bag)Brief only
We supplyBag, envelope, string, tagTea, blend, bag, everything
Clock startsDeposit + artwork + tea at facilityDeposit + recipe brief
Best case2 weeks8 weeks
Typical first run3-4 weeks11-13 weeks
Main delay sourceArtwork, tea transitRecipe revisions, buyer sign-off
Good forSpeed to market, proven recipeBrand launch, proprietary blend

Planning your production calendar

Work backward from your delivery deadline:

Co-packing: add 4-5 weeks from order confirmation to goods in your warehouse (EU destination). If your retailer needs goods by week X, your order confirmation should be no later than week X minus 5.

Full production: add 14-16 weeks from brief submission to goods in your warehouse for a first run. Repeat runs on an approved recipe drop to 8-10 weeks because recipe and artwork approvals are already done.

If you have a trade show, a seasonal launch, or a retailer planogram date driving your deadline, share that date with us at the first conversation. We work backward from hard deadlines and flag early if the timeline is not achievable so you can adjust.

The tools page has an interactive lead time calculator if you want to map your specific scenario. For a direct conversation about your timeline and whether your launch date is achievable, contact us with your target date and a brief on your project.

If you are still comparing co-packing versus full production on cost - not just time - the tea co-packing pricing post and the MOQ and unit price table cover the financial side.

Since 1990Family herb business36 years to DE · AT · CHNow packaging tea
Talk to us

Talk to us about your tea project

Phone, WhatsApp, or send a message. We answer Mon-Fri 09:00-18:00 CET in English, Albanian, Macedonian, and German.